New Air Cooled Chiller Rehabilitation

King Faisal Specialist Hospital

  • slide

PROJECT DETAILS


  • Client King Faisal Specialist Hospital
  • Project New Air Cooled Chiller Rehabilitation
  • Location Riyadh
  • Contract Period 24 Months (22/02/2010 - 21/02/2012)
  • Contract Value SR. 17,405,194


PROJECT DESCRIPTION


New Air Cooled Chiller Rehabilitation

Construct approximately 1000 meter (1.5 M x 2M) concrete trenches; Supply and install around 2000 Meter metal pipes (sizes varying 8” upto 14”) with insulation; Supply and install eight (8) 350 TR YORK chillers; Supply & install eight (8) 1115 gpm centrifugal pumps; Construction of two (2) electrical substations with electrical equipments, such as four (4) 2500 kVA transformers, two (2) switch gears, electrical cabling, lighting the trenches; Testing & commissioning